T2, Dublin Airport

Arup

New terminal building.

Contract advice and claim defence.

Dublin, Ireland

Transport

€690m 

The design, construction and commissioning to operational readiness of a new terminal to process 10 to 15 million passengers per year. The project was procured under 18 separate construction management contracts for individual work packages. 

Image © Jody ODea.